A63 Hull – Augerboring

A63 Castle Street Hull

Written by

bubble design

Published on

28 July 2026

Introduction

HB Tunnelling supported Balfour Beatty by installing a drainage pipe from the new underpass at the modified Mytongate Junction, linking it to the pump station shaft. The original plan to use a micro-bore TBM for a 1200mm ID pipe-jacked tunnel proved unfeasible due to bridge works preventing TBM removal. Instead, we were commissioned to design a 730mm ID auger-bored connection, including reinstatement of tunnel eyes at the shaft and diaphragm wall, and a headwall to support the pipe opening.

To complete the connection, several challenges had to be overcome. The 42.9m tunnel passed beneath the live A63 carriageway and through the shaft wall. Ground investigations revealed weak alluvial clays and silts at tunnel level, with granular alluvium and glacial till beneath.

Augerboring

Objective

Preparatory works included draining the shaft, installing a temporary concrete base, and designing and installing grout blocks outside the structures to provide soft eyes to launch and retrieve the auger through. This was required due to the soft nature of the ground behind the walls and the concern that, when the tunnel eyes were removed, the surrounding material could surge.

The Challenge

Tunnel eyes were cored out and stabilised with shotcrete. A thrust block and auger bore rig were installed in the shaft, and the bore was completed in three phases: pilot rod, 419mm intermediate auger, and final 762mm steel pipe. Pipes were installed in 6m sections, fully welded and inspected. At the reception end, the opening was modified and strengthened with dowels before final pipe installation, monitored throughout to ensure tolerances.

Seals and puddle flanges were fitted, and the annulus grouted with high-strength, non-shrink grout. A 20.5mm UV liner, designed for a 120-year service life, was installed, cured with UV light, and sealed. Minor weld seepage was patched prior to liner installation.

The temporary shaft base was then removed, the shaft cleaned, and benching installed by HBT. HBT managed all shaft works, including daily checks and permit compliance under Balfour Beatty’s system.

The works commenced in September 2025 and concluded in December 2025.

“This was our first time using trenchless technique & HB Tunnelling, we have heard great things about HBT but I can confirm that they are very professional & organised company & we will be looking at the next scheme to use this type of works”
- Persimmon

Case Studies

Related posts

Explore more case studies related to this post.

Bessacarr – Caisson Shafts & Augerbore

HBT undertook the design & build of the foul & storm pump stations & manholes to adoptable standards in accordance with Yorkshire Water requirements.

bubble design

Appleby Lodge – Guided Auger Boring

HB Tunnelling was approached by United Living Energy Ltd (ULEL) to help resolve a potential service clash during the installation of the Appleby Lodge Gas Pipeline.

bubble design

Dinorwig – Timber Heading

HBT was appointed by Morgan Sindall, to undertake the temporary works design and construct a 3.2m long x 1.8m wide x 1.2m high timber heading.

bubble design