Horsham Steel – Augerboring

Horsham Steel

Written by

bubble design

Published on

30 July 2026

Introduction

HBT were approached by a Thames Water Framework contractor to assist with the installation of a 150mm foul pipe beneath an existing carriageway and down the embankment of a railway line, as part of a housing development.

During our site visit, it became clear that access and site constraints posed significant challenges. There was a twin-track railway line in close proximity, along with restricted access to the downstream Thames Water connection manhole.

The client requested that we liaise directly with Network Rail. To comply, HBT undertook the necessary approval process in line with Network Rail procedures.

Augerboring

Objective

HBT were awarded the installation of four shots (three lengths of clay and one shot of 244mm steel, subsequently lined with 180mm OD SDR 11 threaded pipe [150mm ID], with the annulus grouted).

Due to restricted access at the downstream Thames Water connection manhole, a sacrificial steel sleeve was required, and the biscuit had to remain in situ. As part of settlement and heave calculations for Network Rail, HBT elected to use the BM400 rig, which incorporates a semi-closed face system to minimise potential settlement when boring adjacent to railway lines.

The Challenge

Once the settlement calculations had been completed and submitted to Network Rail for approval, works commenced on site. The works involved the installation of three lengths of 50 metres of clay jacking pipe, and one length of 244mm and 150mm NE pipe, 12 metres in total, for the final connection.

All works were completed on programme and within budget.

“We were struggling to see how the works could be completed with all the site constraints. HBT came up with a solution, took the lead with Network Rail, and nothing was too much trouble.”
- Paul Taylor

For more information please contact us on 0845 388 3325 or 07879 624900

Case Studies

Related posts

Explore more case studies related to this post.

Bessacarr – Caisson Shafts & Augerbore

HBT undertook the design & build of the foul & storm pump stations & manholes to adoptable standards in accordance with Yorkshire Water requirements.

bubble design

A63 Hull – Augerboring

HB Tunnelling supported Balfour Beatty by installing a drainage pipe from the new underpass at the modified Mytongate Junction, linking it to the pump station shaft.

bubble design

Appleby Lodge – Guided Auger Boring

HB Tunnelling was approached by United Living Energy Ltd (ULEL) to help resolve a potential service clash during the installation of the Appleby Lodge Gas Pipeline.

bubble design